A returned shop drawing can still have open field dimensions, finishes, equipment data or release authority. Design review and fabrication release are different gates.
The field lesson
Approved does not mean ready to fabricate. A shop drawing review addresses the submitted design; it does not automatically close field dimensions, final finishes, equipment cutouts, or release authority. Before fabrication, use a separate release gate. For every prerequisite, record the evidence, the owner, and the authorized release. If one line is open, hold the affected work. Take risk in life, not on the job site.
Action today
Use a separate release register. For every prerequisite, record the evidence, owner and authorization, and hold only the affected work when a line remains open.